Goodyear demands that the taxpayers of Akron pay them to stay here and the Mayor & City Council approve anything they seem to ask for with their promises they fail to keep.
In the mid 1990′s see the following “Actual Investments Subject to Abatements”
|
Project Name |
Abatement Period |
Investment Subject to Abatement |
% of Abatement |
|
Goodyear Polymer Plant |
1995 – 2005 |
$5,063,943 |
75% |
|
Goodyear Tire Tech Center 1 |
1995 – 2005 |
$8,161,600 |
75% |
|
Goodyear Corporate |
1996 – 2006 |
$32,176,831 |
75% |
|
Goodyear Chemical Pilot Plant |
1997 – 2007 |
$2,954,975 |
100% |
|
Goodyear Campus Expansion |
1999 – 2009 |
$39,064,944 |
100% |
NO COMMENTS
5 Jun 2009